Week 3

This week the team was able to finalize the BoM and send the orders out, during the first half of the week. The BoM had some materials that had to be adjusted because the original BoM did not account for the spare wood in the back. The team was able to find a lot of wooden material for the track, and the BoM was adjusted accordingly.

During the first half of the week, the team discussed a lot about the manufacturing process, ensuring that each member were on the same page. The team also check each other's calculations to validate each others work.

For the last half of the week, the team started the manufacturing phase on what we had at the moment. The team was able to finish constructing the track support columns that would hold up the track, the mold/shape for the wooden track that would be kerfed, and was able to practice kerfing on some spare pieces of wood, in preparation for the upcoming Monday.

There is a lot of things to be manufactured by the team, but the team feels confident in finishing the project. The difficult part is just manufacturing the parts, the assembly of the track would be similar to the straight, wooden mock-up set-up near the beginning of the program.

Comments

Popular posts from this blog

Week 1

Week 2 Update

Research on Past Work