Week 1
Week 1: Design Week Full-Track Expansion Team was able to finish the SolidWorks assembly on the wooden model. When discussing about the wooden model, this includes the previous model that was set-up on the last orientation day, and the track split portion as well. So far, the team has not expand the track for the steel, or actual model because the team decided that the wooden model was more important to focus on. The wooden model is where the full-scale team would try to integrate their design, so the wooden design was given priority. The pure curve section has not been modeled in SolidWorks because if the split has been designed well, the curvature of the turn should be constant. Adding a curve section would be simple, as it is similar to supporting the track as the previous team did for the straight portion. The team encountered a problem regarding manufacturing because the guide rail proposed on the SolidWorks model was simply not feasible to manufacture. The guide rail m