Week 2 Update

The goals for the project on week 2 was to finalize the design and finish the bill of materials (BoM), for the track expansion. All goals were met during this week, where the design was finalized and the BoM was finished. All the listed materials on the BoM totaled to be a little under $800. The track expansion during this time was expected to be more expensive than the previous track (~$500), because the track would be nearly doubling the length of the straight portion. Furthermore, spare wood in the back could also be used to reduce the price of the expansion.

The team also discussed in details on how the track would be assembled, like how each piece of wood would interface to the next. The discussion was important as it would make the assembly phase more smooth, and planned.